Physical Facilities Services on Labor Day

Physical Facilities Customer Service Center and Central Receiving operations will be closed on Monday, September 7 to observe the Labor Day Holiday. Normal operations will resume on Tuesday, September 8.

East Drive Road Closure September 10

East Drive will be closed between Bingham Hall and C4 from 8 a.m. to noon on Thursday, September 10. The closure is needed for delivery concrete for a boiler installation project underway at Bingham. Access to the S lots and parking lot U and deliveries to C4 will be maintained. Signage will be used to redirect traffic during the closure. Contact project coordinator Gregg Konnick with any questions at gkonnick@binghamton.edu or 777-2598.

Center of Excellence B-pod Renovations Begin August 31

Renovations of the B-pod area on the first floor of the Center of Excellence will begin Monday, August 31. The work may create dust, noise and vibrations. Temporary protection will be installed to limit impacts to building occupants as much as possible. The project is scheduled for completion December 11. Contact project coordinator Laura Graden with any questions at lgraden@binghamton.edu or 777-3375.

Schedule Update- Science III Loading Dock Renovations Begin August 31

Work to renovate the Science III loading dock area will begin Monday, August 31. Work will involve removing the existing asphalt drive that leads to the loading dock, installing new sidewalks and curbs on West Drive as well as plantings to screen the dock. When the project is complete, the Science III loading dock will share an access drive with the Science V loading dock. The project will improve pedestrian safety by eliminating a vehicle/pedestrian conflict point. The project will take about a month to complete. During the work, deliveries to Science III will be via the Science V loading dock. Contact Gary Bendert with any questions at gbendert@binghamton.edu or 777-3375.

Utility Relocation Work at ITC August 17 - October 1

Utility relocations for NYSEG and Verizon will be taking place at the ITC complex from Monday, August 17 through Thursday, October 1. Work will involve trenching along Murray Hill Road and up to the NYSEG ECC Building.Temporary fencing will be used for safety. Contact project coordinator Lisa Sklener with any questions at lsklener@binghamton.edu or 759-8276.

Last Updated: 9/4/15