Harpur Quad Excavation October 27

Physical Facilities will be excavating an area of Harpur Quad adjacent to Science I from 7 a.m. to 3 p.m. on Monday, October 27 as we continue investigations into a water leak in underground piping in the area.

University Union Sprinkler Shutdown October 28

There will be a shutdown of the sprinkler system in the University Union from 9 a.m. to noon on Tuesday, October 28. The shutdown is needed to install a sprinkler head. Contact project coordinator Mo Afify with any questions at mafify@binghamton.edu or 777-2828.

Academic A Corridor Project Begins October 20

A small project will begin Monday, October 20 in the 100D corridor in Academic A adjacent to the Student Wing to create space Educational Communications and facilitate a larger project, due to begin in January, that will renovate the Student Wing. The work involves removal of a wall and relocation of a door and will take about a month to complete. Contact project coordinator Jim Barnum with any questions at jbarnum@binghamton.edu or 777-6014.

Whitney/Old Champlain Walkway Work Postponed Until October 28

Work to install a new concrete walk between Whitney and Old Champlain has been postponed until Tuesday, October 28 due to rain and some equipment breakdowns. There will be no pedestrian access between Whitney and Old Champlain during this work. Pedestrians should use other walkways as signage directs. The sidewalk along East Drive closest to Old Champlain will be closed around the work area and pedestrians should use the sidewalk in front of C4 during this time. Traffic will be reduced to one lane periodically throughout the day to allow for concrete delivery. Flag-persons will direct traffic in the area while East Drive is restricted. Contact project coordinator Jennifer Bourassa with any questions at jbourassa@binghamton.edu or 777-5047.

Library Renovations Schedule Changes

Asbestos abatement work taking place in the Library north second floor area is taking a bit longer than originally scheduled. Please note the following adjustments to the previously announced schedule: restrooms 2446 and 2448, the associated corridor outside of the men's and women's restroom and classroom 2449 will be inaccessible beginning Monday October 27. In addition the second floor will not be accessible via elevator 11. Elevator 11 will service all other floors. This particular phase of the project is due to be complete Friday, November 7. The start of this phase is pending completion and final air testing of the ongoing asbestos abatement underway outside elevators 24 & 25. We expect these tests to be complete Friday, October 24. This new work area/phase will not be established until the elevator access to the 2nd floor via Elevator 24 & 25 is available. The main corridor (2400), outside Women, Gender and Sexuality Studies and Writing Initiative, will remain open to any remaining occupants of the 2nd floor. Stair 14 will also remain open. Elevator 24 & 25 will be able to be used (upon completion of testing). Bathroom facilities located near the tower and/or on the 1st floor near Stair 10 and Stair 13 can be used during this time. Contact project coordinator Jennifer Bourassa with any questions at jbourassa@binghamton.edu or 777-5047.

Center of Excellence Door Access September 15 - November 15

Due to work associated with construction of the Smart Energy R&D Building, the overhead door and door adjacent to it in the Center of Excellence will be unavailable from Monday, September 15 through Saturday, November 15. Signs will be posted to indicate this closure. Contact Lisa Sklener with any questions at lsklener@binghamton.edu or 759-8276.

 

Last Updated: 10/24/14