Center of Excellence

The exterior curtain wall and metal panel system is being installed as well as skylights. Electrical work is nearly 60 percent complete. Wire is being pulled to transformers. Drywall is 75 percent complete in the A-Pod and continuing in the B- and C-Pod. Interior framing is 85 percent complete. All penthouses are being painted. The air handling units are arriving and being installed. Pumps, boilers and heat exchangers have been set and are being piped. All piping is nearly complete.