Old O'Connor Johnson Vestibule Work April 20-April 24

There will be a partial shutdown of the vestibule of the main entrance of Old O'Connor Johnson from Monday, April 20 through Friday, April 24. Part of the entrance will remain accessible at all times. The partial shutdown is needed to complete some flooring work. Contact project coordinator Renee Andrews with any questions at randrews@binghamton.edu or 777-3317.

Physical Facilities Encourages Use of Resource 25 for Scheduling

Physical Facilities would like to encourage those who schedule events/activities in campus facilities to enter the event details in Resource 25. Physical Facilities uses Resource 25 to schedule HVAC (heating, ventilation, air conditioning) systems for maximum efficiency.

Nature Pavilion Work Begins April 6

Work to construct a nature pavilion overlooking the Nature Preserve will begin Monday, April 6. The pavilion will be adjacent to the bench currently overlooking the Preserve and across from parking lot M0. A 20 by 12 foot covered deck will be built with room for two picnic tables. The work will take two to three weeks to complete. Contact Director of Design Jesenko Muftic with any questions at jmuftic@binghamton.edu or 777-5259.

Retaining Wall Installation Smart Energy Research and Development Facility April 6- April 24

A retaining wall is being constructed along the east side of pod D at the Smart Energy Research and Development Facility. The work may affect egress around the overhead door at the Center of Excellence. The work will continue through April 24. Contact project coordinator Lisa Sklener with any questions at lsklener@binghamton.edu or 759-8276.

Connector Road Closed Until Spring

The Connector Road through the Nature Preserve is now closed until spring.


 

Last Updated: 4/17/15