Old O'Connor Sprinkler Shutdown July 7

The sprinkler system in Old O'Connor will be shutdown 7 a.m. to noon on Tuesday, July 7. The shutdown is needed to relocate sprinkler heads. Contact project coordinator Renee Andrews with any questions at randrews@binghamton.edu or 777-3317.

Parking Lot T Closed July 6-July 10

Parking Lot T is generally closed this week, July 6 through July 10, due to office moves taking place to Old O'Connor. Contact project coordinator Renee Andrews with any questions at randrews@binghamton.edu or 777-3317.

East Campus House Gas Pipe/Boiler Installation Work Begins July 9

Installation of a gas line to feed the East Campus Housing buildings will begin Thursday, July 9. The line is being installed from West Drive in the area of parking lot C up Center Drive to the Administration Building. This area is noted on our projects map on the Physical Facilities website

Traffic in the area of the work will be reduced to one lane in each direction. Access to parking lots and the Parking Structure will be maintained though there may be delays/one lane access at times. In addition to the work in the roadways, excavation will be taking place at Bingham Hall. Fencing will be put up around the work area and some sidewalks adjacent to the building will be closed. Signs for pedestrian detours will be posted. The excavation is taking place to establish a foundation for a chimney that will be added to Bingham to accommodate additional boilers that will be installed later this year. Work on the gas line installation and excavation around Bingham is scheduled for completion August 14. Contact project coordinator Gregg Konnick with any questions at gkonnick@binghamton.edu or 777-2598.

Old O'Connor Johnson Weed Control Applications July 7 through July 11

Weed control applications will be make in planting beds around Old O'Connor Johnson from Tuesday, July 7 through Saturday, July 11, weather permitting. Contact project coordinator Renee Andrews with any questions at randrews@binghamton.edu or 777-3317.

Site Lighting Work Begins June 24

Light poles along the campus roadway between Mohawk and Nelson A. Rockefeller Center will be moved beginning Wednesday, June 24. The work is expected to take about a week to complete. There may be some pedestrian detours around the work. Contact Tom Seidel with any questions at tseidel@binghamton.edu or 777-4468.

Academic Complex Masonry Repairs Begin June 29

Masonry repairs will take place on walkways near the Academic Complex beginning Monday, June 29. There may be limited pedestrian access around the work area. The work will take about two weeks to complete. Contact Phil Campon with any questions at pcampon@binghamton.edu or 777-2916.

Fire Hydrant Testing Begins June 29

Flushing and testing fire hydrants throughout campus will begin Monday June 29, weather permitting. The testing will continue for about two weeks and will result in water flowing near hydrant locations. There may also be slight water discoloration associated with the testing. Please allow water to run continuously until water is clear. Contact Chris Lewis with any questions at 777-4481 or lewis@binghamton.edu.

University Union Walk-in Cooler Installation

Work will take place near the University Union loading dock in rooms 175, 176 and 176A to allow for installation of a walk-in cooler. The work is expected to begin the week of May 18 and take about two months to complete. Contact project coordinator Jim Barnum with any questions at jbarnum@binghamton.edu or 777-6014.

C4 Can Washing Station Installation

Work to install a can washing station in the dish room of C4 will take place beginning the week of May 18. The work will take about a month to complete. Contact project coordinator Jim Barnum with any questions at jbarnum@binghamton.edu or 777-6014.

Last Updated: 7/6/15