Search Target

2018 Construction/Staging Map

Renovations to Corliss Avenue

The bid process is underway for the renovation and construction of an addition to 48 Corliss. A bid will be awarded in early January with construction to follow. The renovation of the first four floors will create classrooms, simulation labs, offices, advising and conference space, an information commons, food service and public space for the Decker School of Nursing. The addition will house an elevator/stair tower, lobby, classrooms and mechanical room. Floors five and six will be shelled out for future nursing program expansion. Work will be complete in August 2020.

Pharmacy Basement Facilities

Work is underway in the basement of the School of Pharmacy to create hub facilities for the Health Sciences Campus for University Police, Environmental Health and Safety and Information Technology. Offices and conference rooms are being framed and work is about 25% complete. The spaces will be ready for occupants in March.

Pharmacy R&D Building

Design is about 60% complete on the Pharmacy R&D building. The facility will support School of Pharmacy research efforts and be connected to the SOP. Utility infrastructure is being coordinated and work is expected to begin in summer 2019 with completion in 2020.

Upgrade Site High Voltage Phase 6

This project upgrades underground manholes, conduit duct banks and high voltage cables for the Science Complex. The contractor has installed a new duct bank in the area of Science 1 and Academic B. Most work in that area is complete though the contractor will return in the spring to pave areas affected by the project and restore the site. The contractor is active in the area between Science 2 and Science 3 constructing concrete pads for new transformers. Work will also occur in building electrical rooms.

Science 2 Renovation Phase 1

The bid for this project has been awarded and work will get underway in early 2019. Phase one will renovate the entire Physics wing of this 50 year old building. The project will include new multi discipline undergraduate labs, classrooms, restrooms, energy efficient exterior fenestration and updated MEP building systems including air conditioning. The project is expected to be complete in 2020.

Engineering Building Renovation Phases 4&5

The bid for this project has been awarded and work will get underway in early 2019. This critical maintenance project will renovate 66,000 square feet of space in the Engineering Building. Improvements include: Upgrades to HVAC systems including new air handlers, chiller and duct work. Upgrades to power panels, lighting controls, fiber optics and emergency generators. New ADA compliant offices, classrooms and restrooms. New exterior cladding with insulated panels and new windows.

Science 2 Tower Renovation

The scope of work for this project is still being developed, but will include gutting spaces on floors three through eight with complete renovation of that space. A number of critical maintenance items will be addressed including asbestos abatement, new mechanical, electrical, plumbing and HVAC systems. The building exterior will be reclad enhancing energy efficiency under the phase I, of the Physics wing renovation project.

Rehab Science Greenhouses

This critical maintenance project will reorganize the research layout of the greenhouses and create a new entrance. Window glazing panels/system will be replaced along with mechanical components including venting, cooling and water distribution systems.

Library Third Floor Renovations

This project entails a complete gut and renovation of Library South third floor including asbestos abatement and installation of new flooring, ceilings and lighting. Mechanical systems serving the area will be replaced/upgraded including air handlers and chiller. The energy management system will also be upgraded so energy systems can be better managed and costs reduced. The third floor will be connected to existing south stair tower.

Engineering Building Renovation Phases 4&5

This critical maintenance project will renovate 66,000 square feet of space in the Engineering Building. Improvements include: Upgrades to HVAC systems including new air handlers, chiller and duct work. Upgrades to power panels, lighting controls, fiber optics and emergency generators. New ADA compliant offices, classrooms and restrooms. New exterior cladding with insulated panels and new windows.

Onondaga Renovation

Asbestos Abatement and majority of selective demolition has been completed. Wall layouts in core and suite bathrooms is underway. Some framing work is underway. Work is also occurring on rough-ins for mechanical and electrical infrastructure. The overall project entails renovation of bathrooms, lounge areas and corridors with new ceilings, flooring and lighting. New doors and hardware will be installed and exterior masonry repairs are included in the work. Onondaga renovations will be complete for the fall 2019 semester.

CIW Community renovations involve asbestos abatement, renovation of bathrooms including upgrades to building MEP systems. Lounge areas and corridors receive new ceilings, flooring and lighting. Lights in bedrooms replaced with energy efficient LED's, rooms and corridors are painted and several hundred new doors/hardware installations are part of the project along with exterior masonry repairs. Renovations have been completed in Seneca and Cayuga and work is now underway in Onondaga.

Last Updated: 12/12/18