Search Target

Renovations to Corliss Avenue

The contractor has begun work at 48 Corliss Avenue. The site is fenced and old windows are being removed. Flooring is also being removed inside to begin the process of installing new utilities. Excavation will be underway soon on an addition that will house an elevator/stair tower, lobby, classrooms and mechanical room. The renovation of the first four floors will create classrooms, simulation labs, offices, advising and conference space, an information commons, food service and public space for the Decker School of Nursing. Floors five and six will be shelled out for future nursing program expansion. Work will be complete in August 2020.

Corlissday  Lobby 

 

Pharmacy Basement Facilities

Finishing work is underway in the Pharmacy basement including painting, tile work and flooring. This project is providing hub facilities for the Health Sciences Campus for University Police, Environmental Health and Safety and Information Technology. Work will be complete later this spring.

Pharmacy R&D Building

The campus is working through the design and estimate process with the consultant. The facility will support School of Pharmacy research efforts and be connected to the SOP. Work is expected to begin in summer 2019 with completion in fall 2020.

Upgrade Site High Voltage Phase 6

This project upgrades underground manholes, conduit duct banks and high voltage cables for the Science Complex. Most of the exterior work, with the exception of site restoration, is complete. The contractor is now focused on equipment installations in Science buildings.

Science 2 Renovation Phase 1

Asbestos abatement is complete and demo work is underway. The entire Physics wing is being renovated to provide multi discipline undergraduate labs, classrooms, restrooms, energy efficient exterior fenestration and updated MEP building systems including air conditioning. The project is expected to be complete in 2020. 

Science 4 Renovation Phase 2

Schematic design is underway to renovate the west half of Science 4. Renovation of the east side was completed in 2018.  The project will involve installation of new mechanical systems for the west side of Science 4 and renovation of office space, laboratories, and support space. Design will continue through much of 2019 with construction anticipated to begin toward the end of the year.

Engineering Building Renovation Phases 4&5

The contractor has completed demolition and mechanical system rough-ins are also complete. Framing for walls is progressing and dry wall work will be underway soon. Upgrades to HVAC systems including new air handlers, chiller and duct work are part of the project. Upgrades to power panels, lighting controls, fiber optics and emergency generators and new ADA compliant offices, classrooms and restrooms are part of the renovation as well as new exterior energy efficient cladding with insulated panels and new windows. The project will renovate 66,000 square feet of space in the Engineering Building. Work will be complete at the end of 2020.

Science 2 Tower Renovation

The scope of work for this project is still being developed, but will include gutting spaces on floors three through eight with complete renovation of that space. A number of critical maintenance items will be addressed including asbestos abatement, new mechanical, electrical, plumbing and HVAC systems. The building exterior will be reclad enhancing energy efficiency under the phase I, of the Physics wing renovation project.

Rehab Science Greenhouses

This critical maintenance project will reorganize the research layout of the greenhouses and create a new entrance. Window glazing panels/system will be replaced along with mechanical components including venting, cooling and water distribution systems.

Library Third Floor Renovations

This project entails a complete gut and renovation of Library South third floor including asbestos abatement and installation of new flooring, ceilings and lighting. Mechanical systems serving the area will be replaced/upgraded including air handlers and chiller. The energy management system will also be upgraded so energy systems can be better managed and costs reduced. The third floor will be connected to existing south stair tower.

Onondaga Renovation

Finishing work has begun with painting in bedrooms and hallways. Work to install walls in shower areas is progressing along with framing in the main lobby. Ceilings are being constructed in lounge areas. In general, CIW community renovations involve asbestos abatement, renovation of bathrooms including upgrades to building MEP systems. Lounge areas and corridors will receive new ceilings, flooring and lighting. Onondaga renovations will be complete in summer 2019

CIW Community renovations involve asbestos abatement, renovation of bathrooms including upgrades to building MEP systems. Lounge areas and corridors receive new ceilings, flooring and lighting. Lights in bedrooms replaced with energy efficient LED's, rooms and corridors are painted and several hundred new doors/hardware installations are part of the project along with exterior masonry repairs. Renovations have been completed in Seneca and Cayuga and work is now underway in Onondaga.

Hinman Dining Hall Renovation

Work will involve demolition of all interior spaces and construction of an addition on the west side of the Hinman Dining Hall. New interior and exterior finishes and furnishings
and new programming, retail and lounge space are also included in the project.
Additional restrooms and a new elevator in the addition are also part of the project.
The renovation will also provide the building with new mechanical, electrical and plumbing systems. Construction anticipated to begin summer 2019 and be complete fall 2020.

Cleveland Renovations

Design is progressing for a project that will renovate Cleveland Hall in the Hinman Community. Work will include new mechanical, electrical and plumbing systems along with new ceilings, lighting, flooring and doors. Also included in the project is the renovation of bathrooms, new windows and building insulation. The building will have a new roof and elevators will be refurbished as well. Air conditioning will also be installed. Construction is due to get underway in summer 2019 and be complete for the fall 2020 semester.

Last Updated: 3/20/19